Related Jobs
If related jobs are added while recording a job, it is revealed that these jobs will move together.
Path: PMS > Project Management > Jobs
By clicking the "+" button on the Jobs page, you can go to the jobs registration screen.
Jobs; It is divided into two as "upper job" and "sub job". A parent job can have multiple related child jobs.
If; If a sub-job is created depending on the parent job, it is necessary to select "Related Job" under the "Additional Information" tab on the registration screen.

Relational Jobs are grouped under 4 main headings.
The selections made on the start and end times of the child job on this selection screen affect the start and end times of the parent job.
Choices That Can Be Made Depending on the Relationship Type
1) In the "Finish to Start " choice; difference between the start and end time of the parent job; is added to the finish date of the parent job. Completion date of the sub-work; becomes the new start date of the parent job.
F.S: Let the start date of our created parent job be 5.01.2021 end date 10.01.2021 . Let's say the start date of our sub-job is 7.01.2021, and the end date is 9.01.2021.
When the relationship type of the sub-job is selected and saved as "Finish to Start"; The start date of the parent job is updated to 9.01.2021 . Completion date of the parent job; It increases by the difference between the start and end date and becomes 15.01.2021 .
2) In "Start to Finish" select ; The end date of the parent job is updated to the start date of the child job. Start date of the parent job; It is updated by subtracting the start date of the sub-job from the difference between the end and start date of the parent job.
S.F: Let the start date of our created parent job be 20.01.2021 and the end date 30.01.2021. Let's say the start date of our sub-job is 25.01.2021, and the end date is 26.01.2021.
When the relationship type of the sub-job is selected and saved as "Start to Finish" The start date of the parent job is (30-20=10) 15.01.2021 and the end date is 25.01.2021 .
3) In selecting "Start to Start " ; The start date of the parent job is updated as the start date of our child job. Completion date of the parent job; It is updated by adding the difference between the end and start date of the parent job to the start date of the child job.
FAQ:The start date of our created parent job10.01.2021 end Let the date be 20.01.2021 . Let's say the start date of our sub-job is 15.01.2021, and the end date is 17.01.2021.
When the relationship type of the sub job is selected and saved as "Start to Start" The start date of the parent job is 15.01.2021 and the end date is 25.01.2021 .
4) In selecting "Finish to Finish" ; Start date of the parent job; It is updated by subtracting the difference between the end and start date of the parent job from the end date of the child job. Completion date of the parent work; is updated as the finish date of the subjob.
F.F: Let the start date of our created parent job be 15.01.2021 and the end date is 30.01.2021 . Let the start date of our sub-job be 20.01.2021, and the end date be 22.01.2021 .
When the relationship type of the sub-job is selected and saved as "Finish to Finish" The start date of the parent job is 7.01.2021 and the end date is 22.01.2021 .